HERC announces amendments to the Renewable Purchase Obligation Regulations 2017
Haryana Electricity Regulatory Commission recently announced partial amendments to the (Terms and Conditions for determination of Tariff from Renewable Energy Sources, Renewable Purchase Obligation and Renewable Energy Certificate) Regulations, 2017. This is the second amendment of the regulation. The new
Analysis of the Rajasthan High Court Order in Petition Challenging the Validity of the DSM Regulations
The Rajasthan High Court pronounced its judgment recently in a petition that challenged the validity of the Forecasting, Scheduling, and Deviation Settlement Mechanism regulations 2017, of the state (referred to as “DSM Regulations”). In the petition, wind generators had argued
Haryana announces its final DSM regulations for wind and solar, 2019
Haryana Electricty Regulatory Commission announced the DSM regulations for wind and solar, 2019 along with the statement of reasons recently post the draft discussion paper in 2018. The summary of the regulations is as below: Title: Haryana Electricity Regulatory Commission (Forecasting,
CERC notifies sixth amendment of inter-state sharing regulations of transmission charges & losses, 2010
In a recent notification issued by CERC on the (Sharing of inter-State Transmission Charges and Losses) amendments have been announced. These are the sixth amendment in the regulations and will come into effect in retrospection from 31.12.2018. The below-stated amendments
Uttar Pradesh announces Deviation Settlement Mechanism Regulations, 2018
Uttar Pradesh Electricity Regulatory Commission (UPERC) recently announced the (Forecasting, Scheduling, Deviation Settlement and Related Matters of Solar and Wind Generation Sources) Regulations, 2018 The key points of the regulations are as below: The regulations are applicable to all solar (excluding
Gujarat announces RE Forecasting and Scheduling regulations, 2019
Gujarat Electricity Regulatory Commission has recently issued Forecasting, Scheduling, Deviation Settlement, and related matters of solar and wind generation sources regulations, 2019 on 19th January 2019. The notifications are effective from the date of notification, however, the deviation charges specified
TSERC announces APPC cost for FY 2018-2019
Telangana State Electricity Regulatory Commission (TSERC) announces its average pooled purchase cost for the year FY 2018-19. The APPC cost of INR 4.097/kWh for FY 17-18 will be continued for this financial year as well. In an order followed by
CERC announces regulations for implementation of Interstate Transmission System in the country
The Central Electricity Regulatory Commission (CERC) recently announced a regulation called the Central Electricity Regulatory Commission (Planning, Coordination and Development of Economic and Efficient Inter-State Transmission System by Central Transmission Utility and other related matters) Regulations, 2018 which came into
Andhra Pradesh Government asks the state discoms to accept full power from the wind developers
Andhra Pradesh Government has asked the state DISCOMs to take all the power the wind developers produce and further pay for it, irrespective of the Capacity Utilization Factor (CUF) of the developer’s project. In one of the state’s order regarding
Maharashtra joins the list of states with final Forecasting and Scheduling regulations
Recently Maharashtra became the latest state to publish final Forecasting and Scheduling (F&S) regulations. These regulations were published in the State Gazette on July 20, 2018. With this, all supposedly "RE rich" states except Gujarat and Tamil Nadu have finalized