Custom html block

Blog

SECI to come up with 750 MW capacity solar power projects in Rajasthan

SECI has announced an RfS for setting up of 750 MW grid-connected solar photovoltaic power projects in Rajasthan. The land, connectivity & long-term open access shall be the scope of the developer. The tender is a “Build-Own-Operate” (BOO) basis where SECI will enter into a Power Purchase Agreement with the successful bidders for a period of 25 years. The power produced through the project is decided to be sold to Rajasthan Urja Vikas Nigam Limited (RUVNL). The summary of the RfS is as below:
 

Document

Charges

RfS document
  • INR 29,500/- (Indian Rupees Twenty-Nine Thousand Five Hundred Only) including GST
Processing fee
  • Rs. 3 Lakh +18% GST for each Project from 10 MW up to 40 MW capacity
  • Rs. 5 Lakh + 18% GST for each Project from 50 MW up to 90 MW capacity
  • Rs. 10 Lakh + 18% GST for each Project from 100 MW and above capacity
Total available capacity 750 MW
Minimum capacity Minimum individual capacities of 10 MW, and shall be set up in multiples of 10 MW.
Commissioning period
  • For project capacity (1-240 MW): Scheduled Commissioning Date (SCD) shall be the date as on 21 months from the effective date of the PPA
  • For project capacity (250 MW and above): the SCD for the Project shall be the date as on 24 months of the effective date of the PPA
Processing fee
  • Rs. 3 Lakh +18% GST for each Project from 10 MW up to 40 MW capacity
  • Rs. 5 Lakh + 18% GST for each Project from 50 MW up to 90 MW capacity
  • Rs. 10 Lakh + 18% GST for each Project from 100 MW and above capacity
Earnest Money deposit Amount: INR 10,00,000/- (Indian Rupees Ten Lacs) per MW per Project to be submitted in the form of Bank Guarantee along with the Response to RfS
Performance Bank Guarantee (PBG) Bidders selected by SECI based on this RfS shall submit Performance Guarantee for a value @ INR 20 Lakh/ MW within 30 days of issuance of Letter of Intent (LoI) or before signing of PPA, whichever is earlier.
Ceiling tariff INR 2.93/ kWh for 25 years.

SECI has issued this RfS in line with the Ministry of Power (MoP) issued “Guidelines for Tariff Based Competitive Bidding Process for Procurement of Power from Grid Connected Solar PV Power Projects” since August 2017.