MPERC(Cogeneration and Generation of Electricity from Renewable Sources of Energy) (Revision-I)
Madhya Pradesh Electricity regulatory Commission (MPERC) recently ordered amendment for its Cogeneration and Generation of Electricity from Renewable Sources of Energy Regulation 2010. The new amendment has defined the minimum quantum of electricity to be procured by all the Obligated Entities
Captive power plant of Bokaro Steel Plant is co-gen : Jharkhand ERC
In an order dated 24th March 2014, state electricity regulator of Jharkhand (JSERC) is of the view that the captive power plant of Bokaro Steel Plant (a unit of Steel Authority of India) can be regarded as a co-generation plant.
DISCOMs not to be fastened with purchase obligation from conventional co-gen plants : APTEL
A full bench of the tribunal on 2nd Dec’13, pronounced a landmark judgment on the issue of fastening of purchase obligation on DISCOMs, for power procurement from fossil-fuel based co-generation (co-gen) units. The petitioner (Lloyds Metal & Energy Ltd) had filed
Status Quo for co-generators
In a key judgement pronounced by Hon'ble APTEL on 17th April 2013 condonation of delay was not granted. The issue relates to a case filed by GERC against Century Rayon/MERC for the order passed by tribunal on keeping co-generation plant