GUVNL announces tenders for 700 MW solar capacity in the state
The Gujarat Urja Vikas Nigam Limited (GUVNL) has tendered 700 MW of grid-connected solar photovoltaic (PV) power project which will be set up at Raghanesda Solar Park - Gujarat (Phase III). Key points from the tender are as below: The
WIND TARIFF HAS HIT A NEW LOW IN A REVERSE AUCTION HELD BY GUVNL
E-reverse auction for grid connected wind project of 500 MW in Gujarat which took place on 21 December 2017 saw the tariffs dipping to a historically low value of Rs 2.44/kWh. This is lower than the price determined in the second auction
GUVNL'S BIDDING FETCHES TARIFF OF Rs 2.65
In a bidding which took place on 19th September 2017 for a 500 MW solar plant of Gujarat Urja Vikas Nigam Ltd. (GUVNL), the lowest price determined was Rs 2.65 per unit. This was slightly higher than the price of
GERC Maintains Leniency over RPO Compliance
The Gujarat Electricity Regulatory Commission (GERC) in its orders Dated 16th Jan 2015, has given relief to the state distribution companies against their RPO compliance for the year 13-14. The summary of the GERC orders is given below: Orders on GUVNL:
GERC Computes Additional Surcharge
Gujarat Electricity Regulatory Commission (GERC) in its order dated 25th September 2014 has computed the additional surcharge payable by the Open Access Consumers for the control period of 1st October 2014 to 31st March 2015. The order has come as per
APTEL's Judgement on Solar Tariffs in Gujarat
Gujarat Urja Vikas Nigam Limited (GUVNL), had filed a petition before Gujarat Electricity Regulatory Commission in 2013, asking for revision in Solar Tariffs determined by the commission in its order dated 29th January, 2010. The state commission, after hearing the
Gujarat DISCOMs approach CERC to seek REC benefits
Gujarat Urja Vikas Nigam Limited (GUVNL) on behalf of DISCOMs , had approached Hon'ble CERC for certain amendments to REC regulations, enabling the former to claim solar RECs as "Eligible Entity" for excess procurement over & above the stipulated RPO
GERC waives RPO shortfall; second year of non-compliance
In a very disappointing order, the Gujarat State Electricity Commission (GERC) decided to waive off the shortfall in RPO for the year 2012-13. In a petition filed by the Discoms, they had asked for a waiver on the grounds that