Telangana recently came up with its net metering regulation for connectivity with the Grid and sale of electricity from the Rooftop Solar Photovoltaic. This Regulation will be applicable to the distribution licensee, an eligible consumer and a third party owner of a Roof Top Solar PV System in the state of Telangana.
 
Following are some of the highlights of the regulations:
 

  • An eligible consumer shall install the grid connected Rooftop Solar PV System of the rated capacity as specified in this Regulation.
  • The tariff payable to an eligible consumer under the net-metering shall be the average power purchase cost of a Distribution Licensee.
  • The net metering facility, as far as possible, of an eligible consumer shall be in three phase service.
  • A single phase consumer is also eligible for net metering up to 3 KW.
  • The capacity of a Rooftop Solar PV System to be installed at the premises of an eligible consumer shall not be less than one Kilo Watt peak (1kWp) and a maximum of One (1) MWp.
  • The quantum of electricity consumed by an Eligible Consumer from the Rooftop Solar PV System under the Net Metering Arrangement shall qualify towards his compliance of Solar RPPO, if such Consumer is an Obligated Entity.
  • The quantum of electricity consumed by the Eligible Consumer from the Rooftop Solar PV System under the Net Metering arrangement shall, if such Consumer is not an Obligated Entity, qualify towards meeting the Solar RPPO of the Distribution Licensee.
  • The unadjusted surplus Units of the solar energy purchased by the Distribution Licensee under the provisions of sub-Para 10.3 shall qualify towards meeting its Solar RPPO.
  • The Rooftop Solar PV System under the net metering arrangement, whether self- owned or third party owned installed on the Eligible Consumer’s premises, shall be exempted from Transmission Charge, Transmission Loss, Wheeling Charge, Wheeling Loss, Cross Subsidy Surcharge and Additional Surcharge.
  • The Rooftop Solar PV System Developer shall retain the entire proceeds of CDM benefits in the first year after the date of commercial operation of the generating station.

 
The regulation can be accessed here.