Custom html block

Blog

Analysis of the changes proposed in the Electricity Act

Analysis of the changes proposed in the Electricity Act
The Electricity (Amendment) Bill 2014 was tabled in the Parliament recently. Once approved, the amendment will bring sweeping changes in the entire electricity sector. Most aspects of the power industry as it stands today will be touched in some way or another.
We have analyzed the impact of the proposed changes in this article. The changes that we have focused on concern the following areas: Renewable Energy, Open Access, distribution of electricity (ie the role of the Discom), and other changes that have significant impact. There are various other changes as well, but those are outside the purview of this article.
Renewable Energy:
The EA Bill 2014 proposes to include the definition of “Renewable Energy Source” and of “Obligated Entities” in the Act. Further, the bill also states that obligated entities may be mandated to
“procure electricity from or any market instrument representing the renewable energy sources”
These changes are significant as they lay to rest the argument that the obligation to meet RPO is not mandated in the Electricity Act 2003 (‘EA’), particularly for open access and captive generation. This is the premise of on-going cases many states and also in the Supreme Court.
Another objection made to the current regulatory set-up is that RECs have no basis as per the EA. Both these shortcomings will have been addressed with the new Bill.
The Bill also proposes various measures to promote RE generation in the country. The most significant of these is that power procured from RE sources under open access will not attract cross-subsidy. This will give a significant boost to the RE market.
Further, the concept of Renewable Generation Obligation (‘RGO’) has been brought in. The bill requires coal based generators to also set up RE generation,
“…which shall not be less than ten per cent. of the thermal power installed capacity”
This generation will also be allowed to be passed through to the discom as bundled power.
A major shortcoming in the existing act has been the interpretation of the ApTel which leaves co-generation out of the application of RPO regulations. This is now proposed to be changed by mandating RPO to be met only though RE and co-generation from RE. Co-gen from other sources is also required to be promoted, but through sale of power to the licensee only (and not through an RPO).
 
Open Access:
Under the current act, open access has been a failure as most states still do not allow open access, and policies in states are unpredictable. Sweeping changes are now proposed in the open access regime. The Bill proposes that OA will be available to all consumers with load of more than 1 MW by default. Such consumers will be allowed to enter into a bilateral agreement for procurement of power.
 
Change in the role of the Discom:
At present the Discom provides the service of last mile connectivity through the distribution system and also supply of power. This role is proposed to be broken up. A consumer will therefore have the choice to choose his supplier. In a distribution area, more than one supplier will be allowed to operate. The retail tariff set by the SERC will act as the maximum tariff, with suppliers allowed to offer a lower than prescribed tariff.
 
Other significant changes:
Penalty clause: A very important change change is in the penalty clause. Penalty for non-compliance of any provision of the act has been raised to Rs 1 crore. Originally, the penalty was Rs 1 lakh. The bill also proposes a reduced penalty of Rs 10 lakhs for RE generators.
 
Most importantly, the Bill specifically mentions the applicability of penalty in case of non-compliance of RPO or RGO. It says that Sec 142 will be applicable in case:
“…..has not complied with the renewable purchase obligation or renewable generation obligation as specified”
 
Development of market: Another important change has been the mandate to promote forward and futures contracts.
Smart grid and ancillary services: The concept of “smart grid” and “smart meters” have also been incorporated.
“Ancillary services” have also been defined, and all generators will be required to keep a certain portion of generation capacity as “spinning reserve”
 
Conclusion
We believe that these changes will have wide and deep impact in the electricity sector. The promotion of RE and removal of road blocks for development of RE and of open access in the country is a welcome step, and one that was long overdue.
The separation of distribution and supply function also signifies a fundamental shift in the way electricity is distributed in the country. However, this change will take time and strong will to implement. This is evident from the fact that after the EA 2003, the State Electricity Boards were required to be broken up. However, in many states they function in conjunction, and often enjoy the protection of the SERCs and state governments, to the detriment of the industry and consumer.
These changes are bold and welcome. The government will now need to focus on implementation and enforcement. Only then the ambitious plans of “Electricity for All by 2019”, “Make in India” and over 100,000 MW of RE capacity will become a reality.
The Bill would be delayed, as the Standing Committee is yet to give its report on the same.
“The Standing Committee will give its report on the proposed Electricity (Amendment) Bill 2014 by April and then we can introduce it in Parliament,” Power Minister Piyush Goyal
 
The copy of Electricity (amendment) Bill can be accessed here.