MERC Determination of Generic Tariff for Renewable Energy for the remaining Tariff Review Period of FY 2015-16
The Maharashtra Electricity Regulatory Commission came up with its Draft order on determination of generic tariff for Renewable Energy for the remaining Tariff Review Period of FY 2015-16, on 1st December, 2015. This Tariff Order will be applicable for New RE Projects to be commissioned during the remaining Tariff Review Period of FY 2015-16 (1 January to 31 March, 2016).
The RE Tariff Regulations specify the Terms and Conditions and the Procedure for determination of Generic Tariff by the Commission. The graph below gives a comparison of the RE tariff determined in year 2014-15 to the RE tariff determined in 2015-16 for wind and mini & micro hydro generating stations.
The Commission has invited Comments, suggestions and objections from the public and stake-holders, including RE Developers, Distribution Licensees, MEDA, electricity consumers, etc. are on this draft Suo Moto Order.
The Order can be accessed here.