KERC has notified Fourth Amendment to KERC (Procurement of Energy from Renewable Resources) Regulations on October 27th, 2016. The draft of the proposed amendment is available in www.kerc.org. The highlights of the amendment are: RPO obligation is on captive plant, grid connected plants and open

KERC has notified Fourth Amendment to KERC (Procurement of Energy from Renewable Resources) Regulations on October 26th, 2016. The draft of the proposed amendment is available in www.kerc.org. The highlights of the amendment are: RPO obligation is on captive plant, grid connected plants and open

Madhya Pradesh Electricity regulatory Commission (MPERC) recently ordered amendment for its Cogeneration and Generation of Electricity from Renewable Sources of Energy Regulation 2010. The new amendment has defined the minimum quantum of electricity to be procured by all the Obligated Entities